A daily target tells you whether an order will ship on time — but only if you find out about a problem long before the end of the day. Most lines track output hourly precisely so that a supervisor can react to a shortfall in the second hour, not discover it in the last hour when it's too late to fix.
Hourly Line Target = (Number of Operators × Target Efficiency % × 60) ÷ Garment SMV
The daily target is simply the hourly target multiplied by the shift's working hours. Because efficiency is never assumed to be 100% (real lines run at a realistic efficiency level, commonly somewhere in the 60–85% range depending on the factory and style), this formula sets a target that's ambitious but achievable, not a theoretical best case nobody can hit.